  1. Ignition OFF, disconnect the harness connector at the I/P Switch Assembly.
  2. Test for infinite resistance between the signal circuit terminal 7 and the ground circuit terminal 3 with the liftgate open switch in the inactive position.
    • If not the specified value, replace the I/P Switch Assembly.
  3. Test for infinite resistance between the signal circuit terminal 8 and the ground circuit terminal 3 with the liftgate disable switch in the inactive position.
    • If not the specified value, replace the I/P Switch Assembly.
  4. Test for less than 3 ohms between the signal circuit terminal 7 and the ground circuit terminal 3 with the liftgate open switch in the active position.
    • If greater than the specified range, replace the I/P Switch Assembly.
  5. Test for less than 3 ohms between the signal circuit terminal 8 and the ground circuit terminal 3 with the switch in the disable position.
    • If greater than the specified range, replace the I/P Switch Assembly.