Component Inspection

  1. CHECK VIAS CONTROL SOLENOID VALVE 2

    With CONSULT-III 

    1. Turn ignition switch OFF.
    2. Reconnect all harness connectors disconnected.
    3. Disconnect vacuum hoses connected to VIAS control solenoid valve 2.
    4. Turn ignition switch ON.
    5. Select "VIAS S/V-2" in "ACTIVE TEST" mode with CONSULT-III.
    6. Check air passage continuity and operation delay time under the following conditions.
      CONTINUITY CHART

      Condition (VIAS S/V 2) Air passage continuity between (A) and (B) Air passage continuity between (A) and (C)
      ON Existed Not existed
      OFF Not existed Existed
      Fig 1: Checking Air Passage Continuity
      G05869939Courtesy of NISSAN MOTOR CO., U.S.A.

    Without CONSULT-III 

    1. Turn ignition switch OFF.
    2. Disconnect VIAS control solenoid valve 2 harness connector.
    3. Disconnect vacuum hoses connected to VIAS volume control solenoid valve 2.
    4. Check air passage continuity and operation delay time under the following conditions.
      CONTINUITY CHART

      Condition Air passage continuity between (A) and (B) Air passage continuity between (A) and (C)
      12 V direct current supply between terminals 1 and 2 Existed Not existed
      No supply Not existed Existed
      Fig 2: Checking Air Passage Continuity
      G05869940Courtesy of NISSAN MOTOR CO., U.S.A.

    Is the inspection result normal? 

    YES: INSPECTION END

    NO: Replace VIAS control solenoid valve 2