Inspection Procedure
WARNING: This page is about a different car, the 2006 Nissan Pathfinder. However, it is still accessible from the selected car via links, so may be relevant.
- SELF-DIAGNOSIS RESULT CHECK
Check self-diagnosis results.
ABS/TCS/VDC CONTROL UNIT POWER AND GROUND SYSTEMS INSPECTIONSelf-diagnosis results BATTERY VOLTAGE Is the above displayed in the self-diagnosis display items?
YES: GO TO 2.
NO: Inspection End.
- CONNECTOR INSPECTION
- Disconnect the ABS actuator and electric unit (control unit) connector E125.
- Check the terminals for deformation, disconnection, looseness or damage.
OK or NG
OK: GO TO 3.
NG: Repair or replace as necessary.
- ABS/TCS/VDC CONTROL UNIT POWER AND GROUND CIRCUIT INSPECTION
Measure the voltage and continuity between the ABS actuator and electric unit (control unit) harness connector E125 and body ground.
ABS/TCS/VDC CONTROL UNIT POWER AND GROUND CIRCUIT INSPECTIONSignal name ABS actuator and electric unit (control unit) harness connector E125 Body ground Measured value Power supply 1 - Battery voltage (Approx. 12V) 32 Ground 16 - Continuity should exist. 47 OK or NG
OK: Check the battery for loose terminals, low voltage, etc. Repair as necessary.
NG: Repair the circuit.