Diagnostic procedure

DTC P2009 [L3] DIAGNOSTIC PROCEDURE

STEP INSPECTION ACTION
1 VERIFY FREEZE FRAME DATA (MODE 12) HAS BEEN RECORDED 
  • Has FREEZE FRAME DATA (Mode 12) been recorded?
Yes Go to the next step.
No Record the FREEZE FRAME DATA (Mode 12) on the repair order, then go to the next step.
2 VERIFY RELATED REPAIR INFORMATION AVAILABILITY 
  • Verify related Service Bulletins and/or on-line repair information availability.
  • Is any related repair information available?
Yes Perform repair or diagnosis according to the available repair information.
  • If the vehicle is not repaired, go to the next step.
No Go to the next step.
3 INSPECT VARIABLE TUMBLE SOLENOID VALVE CONNECTOR FOR POOR CONNECTION 
  • Turn the ignition switch off.
  • Inspect for poor connection (such as damaged/pulled-out pins, corrosion).
  • Is there any malfunction?
Yes Repair or replace the terminal, then go to Step 9.
No Go to the next step.
4 INSPECT VARIABLE TUMBLE SOLENOID VALVE 
Yes Go to the next step.
No Replace the variable tumble solenoid valve, then go to Step 9.
5 INSPECT VARIABLE TUMBLE SOLENOID VALVE POWER SUPPLY CIRCUIT FOR OPEN CIRCUIT 
  • Disconnect the variable tumble solenoid valve connector.
  • Turn the ignition switch to the ON position (Engine off).
  • Measure the voltage between variable tumble solenoid valve terminal A (wiring-harness-side) and body ground.
  • Is the voltage B+  ?
Yes Go to the next step.
No Repair or replace the wiring harness for open circuit, then go to Step 9.
6 INSPECT PCM CONNECTOR FOR POOR CONNECTION 
  • Turn the ignition switch off.
  • Disconnect the PCM connector.
  • Inspect for poor connection at PCM terminal 2I. (such as damaged/pulled-out pins, corrosion).
  • Is there any malfunction?
Yes Repair the terminal, then go to Step 9.
No Go to the next step.
7 INSPECT VARIABLE TUMBLE SOLENOID VALVE CONTROL CIRCUIT FOR SHORT TO GROUND 
  • Inspect for continuity between variable tumble solenoid valve terminal B (wiring-harness-side) and body ground.
  • Is there continuity?
Yes Repair or replace the wiring harness for short to ground, then go to Step 9.
No Go to the next step.
8 INSPECT VARIABLE TUMBLE SOLENOID VALVE CONTROL CIRCUIT FOR OPEN CIRCUIT 
  • Connect variable tumble solenoid valve connector.
  • Turn the ignition switch to the ON position (Engine off).
  • Measure the voltage between variable tumble solenoid valve terminal B (wiring-harness-side) and PCM terminal 2I (wiring-harness-side).
  • Is the voltage B+  ?
Yes Go to the next step.
No Repair or replace the wiring harness for open circuit, then go to the next step.
9 VERIFY TROUBLESHOOTING OF DTC P2009 COMPLETED 
  • Make sure to reconnect all disconnected connectors.
  • Clear the DTC from the PCM memory using the M-MDS.

    (See AFTER REPAIR PROCEDURE .)

  • Perform the KOEO/KOER self test.

    (See KOEO/KOER SELF TEST .)

  • Is the PENDING CODE for this DTC present?
Yes Replace the PCM, then go to the next step.
(See PCM REMOVAL/INSTALLATION .)
No Go to the next step.
10 VERIFY AFTER REPAIR PROCEDURE 
Yes Go to the applicable DTC inspection.
(See DTC TABLE .)
No Troubleshooting completed.