Installation Procedure
WARNING: This page is about a different variant/trim than selected.
- Generator Control Module 3 Phase Cable - Install
- Loosely install the generator control module 3 phase cable mounting bolts.
- Loosely install the generator control module 3 phase cable terminal bolts.
- Generator Control Module 3 Phase Cable Mounting Bolt - Tighten 9 (80 lb in)
- Tighten the bolts in the sequence shown.8 (71 lb in)
- Terminal Cover Seal (2) - Install
- Dust Cover - Install
- Cover (1) - Install
- Loosely install the cover bolts.
- Heat Shield - Install
- Loosely install the heat shield bolts.
- Tighten the bolts in the sequence shown.9 (80 lb in)
- Starter Generator - Install - Starter Generator Replacement
CAUTION:
Refer to Fastener Caution