Installation Procedure
- Install the battery positive cable (3) to the back of the generator and tighten nut (2) to 20 N.m (15 lb ft).
Courtesy of GENERAL MOTORS COMPANY
- Install the battery positive cable (3) to the starter solenoid and tighten nut (2) to 12 N.m (9 lb ft).
Courtesy of GENERAL MOTORS COMPANY
- Install the battery negative cable to the starter and tighten the stud/nut (1) to 25 N.m (18 lb ft).
- Install the drivetrain and front suspension frame skid plate. Refer to Drivetrain and Front Suspension Frame Skid Plate Replacement
.
- Install the battery negative cable nut (1) and the battery negative cable (2), to the chassis frame stud and tighten to 22 N.m (16 lb ft).
Courtesy of GENERAL MOTORS COMPANY
- Install the battery positive cable (2) to the battery positive cable extension cable junction block and tighten nut (1) to 12 N.m (9 lb ft).
Courtesy of GENERAL MOTORS COMPANY
- Install the battery tray. Refer to Battery Tray Replacement .
- Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
- Install the fuse block and battery positive cable cover.