Installation Procedure
- Carefully install the bank 1 intermediate pipe/hose.
- Reconnect the EGR pipe.
Tighten: Tighten the EGR pipe to 60 N.m (44 lb. ft.).
- Install the nuts securing the bank 1 intermediate pipe/hose to the AIR shut-off valve bracket and the transaxle.
Tighten: Tighten the nuts to 9 N.m (80 lb. in.).
- Install the hose and pinch clamp connecting the bank 1 intermediate pipe/hose to the AIR shut-off valve.
- Install the hose and pinch clamp connecting the bank 1 intermediate pipe/hose to the AIR crossover pipe/hose.
NOTE:
Refer to Fastener Notice
in Cautions and Notices.